Lead Demand
Lead demand, or lead-time demand, is the total demand before replenishment arrives and becomes usable. Both customer demand and the delivery time are uncertain. Lead demand is therefore a random quantity: its forecast is a distribution of possible totals, each with a probability.
To turn that forecast into an order, the buyer also needs to account for existing stock, incoming deliveries, later opportunities to replenish, and the costs of buying too much or too little.
Demand over an uncertain duration
Start with fixed dates and quantities. An order placed at the start of June 1 becomes usable at the start of June 4. Demand of 10 units on each of the three days before receipt totals 30 units:
A. The green bars count demand between ordering and receipt. The gray bar falls after receipt and is excluded. The bracket measures the three-day lead time; the sum measures the 30 units demanded during it. The two scales show June dates and elapsed days.
Let \(L\) be a lead time measured in whole days and \(D_t\) the demand on day \(t\). Suppose the replenishment becomes usable immediately after day \(L\). Lead demand is then:
Both the terms in this sum and the number of days being summed are uncertain. Even perfectly steady demand of 10 units a day would produce uncertain lead demand if delivery could take either 3 or 12 days: 30 or 120 units would be needed before arrival.
Summing a daily forecast over a fixed number of days gives an estimate for that fixed duration. It does not account for the supplier arriving early or late. Nor does a sequence of daily averages describe how successive days’ demands vary together.
Combining the two uncertainties
Consider the supplier illustrated in the lead-time article: a 70% chance of a receipt within 2–4 days, and a 30% chance of waiting 10–14 days. The first group corresponds to items shipped from stock; the second includes a wait for the supplier’s own replenishment. Suppose customer demand also varies, averaging 10 units per day.
B. Each line accumulates demand until a possible receipt. Two highlighted examples end with 26 units on June 4 and 108 units on June 13. The shaded bands mark the arrival windows. The histogram below groups demand totals in tens: 20–29 units, 30–39, and so on. Green denotes shipment from stock; orange, shipment after replenishment.
Here daily demand follows a Poisson distribution averaging 10 units, independently across days and independently of lead time. The six paths illustrate possible histories; the distribution below accounts for all possible demand totals and their probabilities.
For each possible arrival day, calculate the distribution of demand accumulated until that day. Weight it by the probability of that arrival, then combine the results. The longer wait exposes stock to more days of demand. In this example, average lead demand is 58 units, but that figure lies between the two main groups of outcomes. Buying to cover the average conceals a substantial chance of needing much more.
In the general case, the calculation must preserve dependencies: between successive days of demand, between successive deliveries, and between demand and delays. The lecture on probabilistic forecasting explains the distributional view; the lead-time lecture shows how to compose demand and arrival forecasts to assess replenishment.
When demand and delays rise together
Suppose a supplier delivers in two days under normal demand, but needs five days during a surge. Each condition lasts until delivery:
| Situation | Probability | Demand per day | Lead time | Lead demand |
|---|---|---|---|---|
| Normal | 80% | 10 units | 2 days | 20 units |
| Surge | 20% | 20 units | 5 days | 100 units |
Average daily demand is 12 units and average lead time is 2.6 days. Multiplying those averages gives 31.2 units, but actual expected lead demand is 36 units: \(0.8 \times 20 + 0.2 \times 100\).
The shortage risk differs even more. Incorrectly treating the two variables as independent creates four combinations:
| Demand per day | Lead time | Implied probability | Lead demand |
|---|---|---|---|
| 10 units | 2 days | 64% | 20 units |
| 20 units | 2 days | 16% | 40 units |
| 10 units | 5 days | 16% | 50 units |
| 20 units | 5 days | 4% | 100 units |
This calculation preserves both individual distributions but invents combinations absent from the example. It claims that 50 units cover demand with 96% probability. The correct probability is only 80%. The 95th percentile of lead demand is 100 units, not 50.
Supplier congestion, shared holidays, and promotions can link demand to delivery times. The forecast must preserve those links. Multiplying separate high percentiles cannot tell us how often high demand and late delivery coincide.
Which period must stock cover?
In a simplified continuous-review policy, replenishment can be ordered as soon as the inventory position reaches a reorder point. This position includes stock on hand and on order, less unfulfilled commitments. Demand during the lead time then informs that threshold.
With periodic review, stock must also cover the wait until the next ordering opportunity. In the basic model with a fixed review interval \(R\) and fixed lead time \(L\), an order-up-to target covers demand over \(R+L\). This protection period differs from the lead time itself. Weekly review and a two-week delivery delay imply three weeks of coverage at the review date.
Goods ordered today can meet demand only after they arrive. To evaluate the purchase, we must consider demand from that arrival until a later order can take over. Introduction to Supply Chain calls this the window of responsibility. Stock left at its end must still be valued or charged for future holding and disposal costs.
With uncertain lead times, both ends of this window move. Two orders placed a week apart may arrive close together or even in reverse order. The calculation therefore needs distributions of stock remaining at arrival and demand until the next receipt. Forecasting demand over one fixed protection period loses this timing risk.
A stock total can conceal a shortage
Suppose 20 units are available now, another 100 arrive at the start of day 4, and customers request 10 units on each of days 1, 2, and 3. On-hand plus on-order stock is 120 units, far above the 30 units of demand before delivery. Nevertheless, 10 units of demand on day 3 cannot be served on time.
A replenishment calculation must follow consumption and usable receipts in date order, including partial deliveries.
From lead demand to a purchasing decision
The 95th percentile, a quantile, is the smallest quantity sufficient to meet demand with at least 95% probability. Quantiles need not split discrete demand into exact percentages: in the two-outcome example, 20 units cover 80% of cases, so the median also covers 80%.
Coverage probability is also different from the proportion of units served, the duration of a shortage, or its cost. A missing inexpensive accessory and a missing spare part that grounds an aircraft warrant different decisions. A uniform service-level target cannot express those differences.
Lokad evaluates purchases by their expected economic returns, using probabilistic forecasts of demand and deliveries. The calculation includes purchase costs, lost sales, spoilage, and order constraints. Products compete for shared cash and capacity, so a purchase that looks attractive on its own may still lose out to a better use of those resources.