Lead Time
A lead time is the elapsed time between the start and completion of a process. For purchasing, it commonly runs from placing an order until the goods are available for use or sale. Past lead times are measured; future lead times are almost invariably uncertain. Forecasting them means assigning probabilities to possible durations. An ERP field containing “14 days” conceals that uncertainty.
Lead times determine how far ahead a company commits its money and which shortages it can still prevent. A shipment that arrives after the selling season may be almost worthless. Purchasing therefore requires a forecast of when goods might arrive, in what quantities, and what demand they will find.
Start with a fixed arrival date. An order placed on June 1 and available for use on June 4 has a lead time of three calendar days:
A. The document marks the order; the warehouse marks the usable receipt. The arrow spans the three-day lead time. The upper scale gives June dates; the lower scale gives days elapsed since ordering.
Why lead times often have two peaks
A supplier with the item on hand can pick, pack, and dispatch it. A supplier without it must first replenish or manufacture it. These two situations produce different waiting times. Their mixture often gives a bimodal distribution: a short-delay peak for deliveries from stock and a second, more distant peak for deliveries awaiting supply. The lead-time forecasting lecture shows examples of these distributions in operational data.
B. Open circles mark possible receipts for the June 1 order. In this illustration, 70% of orders ship from stock and become usable June 3–5 (green); 30% wait for replenishment and arrive June 11–15 (orange). Each circle aligns with its probability bar. The dashed line marks the 5.8-day average between the arrival windows.
Even within each group, the duration varies. Knowing that an item is in stock does not fix the carrier’s arrival time or the inspection queue. Missing a weekly departure can introduce further peaks; a serious disruption can stretch the tail far beyond normal deliveries. A bell curve centered on the average misses these mechanisms.
For the supplier illustrated above, planning for six days overstates the wait for deliveries from stock and understates it for deliveries awaiting replenishment. Adding a fixed safety margin merely selects another date. It still does not describe the likelihood or severity of late arrivals. The purchasing calculation needs the distribution itself.
Confirmed stock availability, a shipping notice, or a production delay changes that distribution. Without reliable supplier stock data, past receipts can still reveal the two patterns and help estimate their probabilities. Those probabilities must evolve with the supplier’s situation; they are not permanent percentages attached to a SKU.
Where the measurement starts and ends
A duration is meaningful only when its start and end events are explicit. Supplier confirmation, departure from the factory, arrival at the warehouse, and release after inspection are different events. So are the customer’s requested date and the supplier’s promised date: neither is an observed delivery.
| Lead time | Start | End |
|---|---|---|
| Purchasing | Purchase order released | Goods available for use |
| Production | Work order released | Finished goods available |
| Transport | Goods handed to carrier | Goods delivered |
| Customer order | Order accepted | Customer receives goods |
| Repair turnaround | Item sent for repair | Serviceable item returned |
These intervals can overlap. Transport, for example, is already included in the purchasing lead time defined above. Use a consistent calendar for holidays, cutoffs, and time zones. A Friday-to-Monday delivery takes three calendar days, but only one business day under a Monday-to-Friday calendar.
Waiting to place an order also matters. A weekly ordering schedule can add nearly a week before the supplier even receives the order. A minimum order quantity can postpone purchasing until enough demand accumulates. Keep this waiting time separate from supplier performance, while including it in the replenishment decision.
Measuring partial deliveries
For a completed receipt:
A 100-unit order placed on day 0 might arrive in two parts:
| Day | Event | Cumulative units available |
|---|---|---|
| 5 | First 60 units arrive, awaiting inspection | 0 |
| 7 | First 60 units released | 60 |
| 12 | Remaining 40 units arrive, awaiting inspection | 60 |
| 14 | Remaining 40 units released | 100 |
The first usable receipt takes 7 days; completion takes 14. The quantity-weighted average is 9.8 days: \((60 \times 7 + 40 \times 14)/100\). Planning as though all 100 units arrive on day 9.8 would make 40 units available before they have arrived and withhold 60 units already on hand.
Keep order-line quantities, split receipts, and release dates linked. A bookkeeping timestamp may record when someone entered a receipt rather than when stock became available. Preserve original promises and subsequent revisions so that a rescheduled late delivery does not become an apparently punctual one.
Open orders are evidence too
An order still open after 20 days has a lead time exceeding 20 days. Dropping it from the dataset hides the delay while retaining faster, completed orders. This is a right-censored observation: we know how long the order has been pending, but not when it will arrive.
The remaining wait changes as an order ages. In the illustrated distribution, an order still undelivered on June 6, five days after ordering, can no longer belong to the short-delay group. Its possible arrival dates are June 11, 13, and 15, with revised probabilities of one-sixth, one-half, and one-third. There are another 5, 7, or 9 days to wait. Subtracting five days from the original 5.8-day mean would predict less than a day; the updated forecast puts no probability on such an early arrival.
Update outstanding orders using their age, shipment status, and new supplier information. A cancellation or permanent non-delivery is a separate outcome, not an exceptionally long receipt to be assigned an arbitrary duration. For partial deliveries, track both the outstanding quantity and its possible arrival dates.
Forecasting with little history
A product ordered monthly supplies only twelve observations a year; a new supplier supplies none. Forecasting therefore requires learning from other products or suppliers. Similar production methods, routes, order sizes, and calendars can justify sharing observations. A common supplier name alone does not.
Air and sea freight are usually choices, not random fluctuations of one process. Forecast each option separately. Likewise, a large order can take longer than a small one, and a factory shutdown changes the outlook even if last month’s deliveries were punctual.
A probabilistic model must represent the plausible durations, their probabilities, and the long delays that matter for purchasing. Sparse history makes the tail particularly difficult to estimate. It does not justify treating the longest delay observed so far as the longest delay that can occur.
Test forecasts using only information available when they would have been issued. Across comparable orders, do deliveries predicted with 90% probability arrive by the forecast date roughly nine times out of ten? Include pending orders in this check; dropping them would hide failures. Four receipts cannot establish a dependable supplier-specific 95th percentile. The lead-time forecasting lecture explains how to learn from sparse and incomplete observations.
The cost of late arrivals
A 95th-percentile lead time of seven days means that arrival is expected within seven days with at least 95% probability. It says nothing about how late the remaining deliveries might be. Their consequences depend on what the goods are for.
Consider a one-off seasonal purchase of 100 units. All units sell for $20 each if they arrive before a deadline; afterward, they can only be liquidated for $2 each. Assume the following prices include freight and that other costs are identical:
| Supplier | Purchase cost per unit | Probability of timely arrival | Profit if timely | Profit if late | Expected profit |
|---|---|---|---|---|---|
| Standard | $10 | 80% | $1,000 | −$800 | $640 |
| Faster | $12 | 95% | $800 | −$1,000 | $710 |
The faster supplier costs $200 more but earns $70 more in expectation. For the standard supplier, the calculation is \(0.8 \times 1{,}000 + 0.2 \times (-800) = 640\). A cheaper purchase price alone would select the worse option.
The example fixes quantities sold and liquidation prices. In practice, a buyer has to estimate both before he decides how much to order, whether to wait, or whether to split the purchase between suppliers. Extra stock delivered after the season will not recover missed sales.
Demand and supply delays
Demand surges can overload the supplier just when customers want more. Treating demand and lead time as independent then understates the shortage risk. Transport and production delays can also share a cause; adding independently sampled stage durations would lose that connection.
Lead demand is the demand accumulated before replenishment becomes available. Its distribution combines uncertain demand with uncertain arrival dates. An average demand multiplied by an average lead time generally does not suffice, as the companion article’s worked example shows.
Today’s decisions also change tomorrow’s lead times. Consolidating orders saves freight but postpones dispatch; expediting an urgent order can delay other work. A forecast fitted to past choices should not be reused unchanged to evaluate a different purchasing policy.
Improving the process
Longer lead times can accompany lower production or transport costs. They also extend commitments, delay revenue, and leave less room to react. Goods in transit remain part of this commitment even when warehouse stock looks low.
Break down elapsed time to locate avoidable waiting. Orders can spend more time awaiting a batch, an approval, or inspection than in production or transport. Queues tend to become harder to absorb when capacity has little slack. Faster machinery will not fix an approval queue.
Watch the age of unfinished work as well as completed-order averages. Processing recent, easy orders first can improve the reported average while leaving older orders stranded. Giving a critical spare part priority may be worth delaying routine replenishment. Count the cost of that delay.
Lead times by industry
| Operation | What the forecast must describe |
|---|---|
| Fresh food | Arrival date and remaining shelf life; a faster delivery of older goods can be less valuable |
| Maintenance and repair | Return date, quantity repaired, and probability that an item cannot be repaired |
| E-commerce returns | Whether an item returns, when it returns, and whether it can be resold |
| Leasing | Return date and condition, influenced by renewal terms and customer behavior |
At Lokad, forecasts of arrival dates and quantities feed the numerical recipes that choose purchases, transfers, repairs, and expedited shipments. These choices compete for the same cash and capacity. Introduction to Supply Chain explains how to compare their expected returns across the business.